WICKENDEN BUILDING RENOVATIONS:
New State-of-the-Art Facilities for BME Education and Research
Construction plans have been developed and approved, furniture and interior
designs have been selected, and funds have been acquired to start the final phase of
renovations in the Wickenden Building on the Case Quad. Renovation of the 4th floor started Oct 18, 2004, and will be completed in late spring 2005. The north side of the 3rd floor will be
renovated in conjunction with 4th floor renovation. The majority of the 3rd floor will be renovated
starting in summer 2004, excluding the main office. After this phase of 3rd floor renovation is
complete, the main office will move to the newly renovated space on the 3rd floor overlooking
the quad, and the remainder of the 3rd floor will be renovated.
ACCESS RESTRICTIONS
The fourth floor and the north side of the third floor are not accessible. Access to the third floor via the elevator is restricted. These restrictions are in effect until the renovation is completed in Spring 2005.
|
Floor plans have been provided by Brian Miner and John Van Auker of Hasenstab Architects, Inc. Click on selected areas of the floor plans for expanded views.
|